Access Channel for High Speed Integration in Valencia*

Valencia, Spain

1,800,000 m³

Excavations

The project consists of the construction of a new railway access channel to integrate the High Speed in Valencia by burying the existing tracks. In addition, the Valencia Joaquín Sorolla station and its car park are being expanded and remodelled to adapt them to the new railway configuration.
av_canal_acceso_estacion_valencia_6
The project consists of the construction of a new railway access channel to integrate the High Speed in Valencia by burying the existing tracks. In addition, the Valencia Joaquín Sorolla station and its car park are being expanded and remodelled to adapt them to the new railway configuration.
It is a large urban railway work of high technical complexity, with significant volumes of earthworks, structures and track laying.

Project data

·

Execution of tunnels for the burial of the access roads, giving continuity to the South Junction.

·

1,800,000 m³ of excavations

·

350,000 m³ of structural concrete

·

40 million kg of armor

·

17 km of flexible overhead catenary

·

27,000 m of jet grouting and 200,000 m² of continuous containment screens