Port of Hayovel Expansion
Ashdod, Israel
Port
Project type
1150 m
Breakwater length
1700 m
Berth length
14 m
Draft
3.0 Mm³
Dredging volume (m³)
50 Ha
Riprap (m3/t)
The Port of Hayovel Expansion significantly increased port capacity through the construction of new maritime infrastructure, logistics areas and berthing facilities for large vessels.
The project included the extension of the existing breakwater by 1,150 m, protected using Antifer concrete armour units, together with the creation of a 50-hectare reclaimed port platform and the execution of 3.2 million m³ of dredging works.

The development also incorporated five new quays with a combined length of 1,700 m, delivered through several structural solutions including sheet pile walls, piled quays and caisson structures adapted to different operational requirements.




Project data
Project data
·
3,800 ft Breakwater Length
·
125 acres Reclaimed Land Esplanade
·
Dredging: 4 million cy
·
3.2 million m³ of dredging works
·
1,700 m of new quays
·
14 m operational draft
·
Protected with Antifer armour units
·
Five different quay typologies