Madrid Metro Extension

Madrid, Spain

TBM EPB

Construction method

76,000 m

Excavated length

8.43m / 9.38m

Internal Diameter / Excavation

4 TBM

TBM number

Line 11: Plaza Elíptica – Conde de Casal

The Madrid Metro Extension Programme represents one of the largest underground transport developments undertaken in Europe, delivering more than 165 km of new lines and 168 stations between 1995 and 2011.

DRAGADOS is currently delivering the extension of Line 11 of the Madrid Metro, along the section between Plaza Elíptica and Conde de Casal. The contract includes the construction of 7 km of single-bore, double-track tunnel, with an excavation diameter of 9.38 m, executed mainly using an EPB tunnel boring machine, launched and operated from Comillas station towards Conde de Casal.

The project also comprises the construction of five new stations —Comillas, Madrid Río, Palos de la Frontera, Atocha and Conde de Casal— together with seven emergency exits, six ventilation shafts, and five pumping shafts, integrated into different structures along the alignment.

north_west_rail_link_sidney_australia_2019_377_windsor_road_bridge_003

Network Expansion (1995–2011)

Between 1995 and 2011, Madrid Metro carried out the largest expansion in its history, with the construction of more than 165 km of new lines and 168 new stations, requiring the use of 31 tunnel boring machines (TBMs).

Of this total, DRAGADOS delivered 76 km, of which 61 km were excavated using TBMs, more than 8 km were executed using the Cut & Cover method, 2 km using the Belgian method, and 4 km corresponding to stations, also constructed using Cut & Cover and mechanical methods.

Extended Lines

·

Line 1: Miguel Hernández – Congosto

·

Line 4: Esperanza – Mar de Cristal; Mar de Cristal – Parque de Santa María; Parque de Santa María – Gran Vía de Hortaleza

·

Line 7: M-40 – Coslada; Coslada – San Fernando

·

Line 8: Nuevos Ministerios – Mar de Cristal; Mar de Cristal – Campo de las Naciones; Campo de las Naciones – Barajas

·

Line 9: Pavones – Vicálvaro

·

Line 10: Lago – Príncipe Pío; Cuatro Vientos – Alcorcón

·

Line 11: Plaza Elíptica – Pan Bendito; Pan Bendito – Carabanchel; La Peseta – La Fortuna

·

Metrosur: Getafe – Leganés; Leganés – Móstoles
north_west_rail_link_sidney_australia_2018_376_sydney_metro_train_testing_windsor

Project data

·

Total length: 67 km

·

Excavation diameter: 9.38 m (EPB TBM, single-bore double-track tunnel)

·

Internal diameter: 8.43 m

·

Excavated volume: 4.6 million m³

·

5 new stations

·

7 emergency exits

·

6 ventilation shafts

Did you like this project? Share it! 