Ottawa Light Rail
Ottawa, Canada
Conventional with roadheaders
Construction method
2,533 m tunnel and 3 stations
Excavated length
9.0 m
Internal Diameter / Excavation
3 Sandvik MMT-720 Roadheaders
TBM number
The Ottawa Light Rail Transit project includes a 2,533 m underground section beneath downtown Ottawa, incorporating the Lyon, Parliament and Rideau underground stations

As this is a concession contract, the scope goes beyond the design and construction of the infrastructure and also includes the operation and maintenance of the 12.5 km Confederation Line for a period of 30 years.






The Sequential Excavation Method (SEM) was selected for the execution of the entire underground section. Excavation works were carried out using three heavy-duty Sandvik MT-720 road headers, as the alignment runs through limestone formations.
Project data
Project data
·
2,533 m of mined tunnel
·
3 underground stations
·
Constructed using SEM
·
9 m excavation diameter
·
18 m station excavation diameter
·
30-year operation and maintenance concession
·
Part of the 12.5 km Confederation Line
·
Completed in 2017