SR-99 Alaskan Way replacement

Seattle, USA

TBM EPB

Construction method

2.688 m

Excavated length

15.85 / 17.48

Internal diameter / excavation

1 TBM world record

TBM number

50 m below sea level

Depth

The SR 99 Alaskan Way Replacement project involved the construction of a 2,688 m urban road tunnel beneath downtown Seattle using the world’s largest EPB tunnel boring machine at the time of construction.
sr_99_alaskan_way_seattle_eeuu_2020_353
The scheme replaced a major urban transport corridor through a double-deck tunnel with two lanes in each direction arranged on two levels. The alignment runs beneath the city centre and passes below landmark buildings, reaching a maximum depth of 50 metres below sea level.

The tunnel boring machine, of innovative design and Japanese manufacture, incorporated state-of-the-art technologies for cutter replacement and robotic systems, enabling successful excavation under highly demanding geotechnical conditions.

The tunnel lining consists of universal precast concrete segment rings, 60 cm thick and 2 metres long, achieving a final internal diameter of 15.85 metres.

sr_99_alaskan_way_seattle_eeuu_2018_353_13
The project reinforces Dragados’ expertise in large-diameter tunnelling and underground infrastructure delivered beneath highly complex urban environments

Project data

·

2,688 m urban tunnel

·

World's largest EPB TBM at the time

·

17.48 m excavation diameter

·

15.85 m internal diameter

·

646,000 m³ excavated

·

Double-deck road tunnel

·

Up to 50 m below sea level

·

60 cm thick precast concrete lining

·

World-record EPB excavation diameter

·

Completed in 2019